Current Waterworks Projects

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

The City of Simi Valley/Ventura County Waterworks District No. 8 (District) is committed to delivering high-quality drinking water to over 26,000 residential, industrial, and commercial service connections. The District operates an extensive potable water system within the City of Simi Valley and some unincorporated areas in Ventura County. The District’s projects consist of facility rehabilitation and replacement of aging infrastructure in addition to improvement of the District’s water distribution and storage system to meet the current design and regulatory standards.

COMPLETED PROJECTS

SV 23-16, WALNUT TANK 2 REPAIR AND RECOAT

SV 24-10, WATER LINE REPLACEMENT - APRICOT/CEDAR/LEOTA (WISTERIA)/ EASTWARD/MY WAY (ROWELL)

PROJECTS UNDER CONSTRUCTION

SV 24-16, WATERLINE REPLACEMENT - VARIOUS LOCATIONS IN THE SANTA SUSANA KNOLLS

 Status: In Construction

  • This project will install approximately 5,354 feet of pipeline in various locations in the Santa Susana Knolls Area. The new pipelines will replace 2-inch, 4-inch, 5-inch and 6-inch steel and Polyethylene Pipe (PEP) pipelines that have been repaired several times by Waterworks District staff in response to emergency failures.

 SV 25-34, EMERGENCY GENERATORS PROJECT

 Status: In Construction

  • The project consists of the construction of emergency small generators of approximately 20 kW at four (4) existing reservoir sites: (Walnut, Madera, Mellow Lane, and Box Canyon). The objective of this project is to provide emergency power at these sites to power small loads generally consisting of the SCADA system, radios, seismically actuated valves, and, if feasible, motor operated gates. The back-up emergency power is needed to maintain operations at these sites in the event of Southern California Edison (SCE) Public Safety Power Shutoffs (PSPS) as well as other unscheduled power outages.

PROJECTS IN DESIGN & BID PHASE 

SV 21-03, KNOLLS ZONE WATER FACILITIES PROJECT

 Status: Design Phase

  • This project would design and construct a new 1.0-million-gallon water storage tank to increase fire storage capacity and supply water at a higher pressure to some higher elevation lots in the Knolls Pressure Zone. The tank will be located on property acquired in the Knolls Zone. The project also includes the installation of approximately 1,100 feet of 10-inch pipeline to supply water from the proposed tank to the existing Alta Vista tanks.

PW 20-14, OAK KNOLLS PUMP STATION UPGRADE PROJECT

 Status: Design Phase

  • The pump station is the primary source of water supply for the Knolls (1404) Pressure zone and is more than 50 years old. This project would upgrade the existing Oak Knolls Pump Station by replacing the single 380 gallons per minutes (gpm) pump unit with larger pumps. The project will also consist of the construction of a new pump building, upgrading the electrical equipment, installing two new pumps and motors, and replacing the existing piping to ensure the reliability of the pump station.

 PW 21-02, BOX CANYON PUMP STATIONS 1 AND 2 REHABILITATION PROJECT

 StatusDesign Phase

  • The Waterworks Facilities Assessment identified problem areas at the Box Canyon Pump Stations due to aging infrastructure. This project would rehabilitate Pump Stations No. 1 and No. 2. to improve system functionality and reliability. The project will also include the installation of approximately 4,600 linear feet of new water transmission line between Pump Station 2 and Box Canyon reservoir. The new pipeline will replace an existing 12-inch welded steel and asbestos cement pipeline originally constructed around 1964. The pipeline requires replacement due to its age, inaccessibility, and likelihood of failure.

PW 25-01, STOW NO. 1 TANK REPLACEMENT

 Status: Design Phase

  • This project would replace Stow Tank No. 1, which has been in service since 1975, with a capacity of 1.0 million gallons. The Seismic Evaluation of the Waterworks Storage Tank System identified seismic deficiencies and recommended replacement of this tank with a new welded steel tank that meets the current seismic code requirements.

PW 25-04,SEISMIC RETROFIT OF TWO WATER TANKS

 Status: Design Phase

  • This project would upgrade the piping and mitigate seismic deficiencies for the 426,000 gallon Stearns Tank and 2.5-million gallon Madera Tank. The Seismic Evaluation of the Waterworks Storage Tank System conducted by Kennedy Jenks in 2020 identified the seismic deficiencies of the tanks and recommended that each be retrofitted to meet current seismic code requirements and ensure reliability of the system.

 

 *Note: Projects & schedules are subject to change. 

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Windows Media Player Download Windows Media Player Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer